4E projects budget
From SlugWiki
4E Projects passed for $100 in the Fall 2005 budget. The project ran over budget due to drill bits wearing out; GRT funding made up the difference of $30. The itemized budget is shown below:
Item | Price |
concrete anchors | $28 |
wall anchors | $6 |
masonry drill bits | $26 |
threaded rod, nuts, etc. | $18 |
conduit, boxes, etc. | $27 |
dremel disks | $7 |
cable ties | $8 |
tax, rounding error, misc. | $11 |
Total | $131 |